Study Milestones
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 09-Mar-00 | Study Team Initiation | |
| 21-Jun-00 | Development of Conceptual Plans Complete | |
| 26-Jan-01 | Formulation of Alternative Plans Complete | |
| 26-Jan-01 | Initiate Alternative Plan Analyses | |
| 30-Mar-01 | Alternative Plans Analyses Complete | |
| 20-Apr-01 | Initiate Recommended Plan Development | |
| 13-Jun-01 | Recommended Plan Development Complete | |
| 7-Sep-01 | Complete Preliminary Draft Feasibility Report | |
| 7-Sep-01 | Complete Preliminary Draft EIS (PDEIS) | |
| 10-Sep-01 | Initiate Review of Preliminary Draft Feasibility Report | |
| 25-Sep-01 | Initiate Review of Preliminary Draft Environmental Impact Statement (PDEIS) | |
| 30-Sep-01 | Complete Review of Preliminary Draft Feasibility Report | |
| 3-Oct-01 | Complete Review of PDEIS | |
| 8-Oct-01 | Initiate Independent Technical Review of Preliminary Draft Feasibility Report and PDEIS (DNR, NOD, MVD, HQ) | |
| 31-Oct-01 | Complete Independent Technical Review of Preliminary Draft Feasibility Report and PDEIS (DNR, NOD, MVD, HQ) | |
| 14-Jun-02 | Complete Draft Environmental, Economic, and Engineering Appendices | |
| 14-Jun-02 | Complete Final Real Estate Plan and Final Real Estate Gross Appraisal | |
| 14-Jun-02 | Complete
Draft Feasibility Report and Draft Environmental Impact Statement |
|
| 1-Jul-02 | Submit Draft Feasibility Report package to MVD and Technical Advisory Committee (TAC) for review | |
| 1-Aug-02 | Initiate
60-day Public Review of Draft Report - Including Public Meetings |
|
| 30-Sep-02 | Complete 60-day Public Review of Draft Report | |
| 31-Oct-02 | Complete Final Feasibility Report Package | |
| Nov-02- | District Engineer's Notice | |
| Nov-02 | Division Engineer's Notice | |
| Dec-03 | Chief's Report |
New
Orleans District of the US Army Corps of Engineers Louisiana Department of Natural Resources
Site Maintained by US Geological Survey
- National Wetlands Research Center
Please report problems with this site to coast2050@condor.nwrc.gov
Privacy Statement | Disclaimer | Freedom of Information Act | Accessibility